Cost breakdown example

50x80 metal shop cost and material list

A full framing, sheeting, and trim takeoff for a 50' × 80' weld-up building: 14' eave, 4:12 pitch, one walk door, two 12'×12' roll-up doors. Generated by Gable Takeoff; every number below is a real output, not a rounded guess.

Width 50 ft
Depth 80 ft
Eave 14 ft
Pitch 4:12
Ridge 22' 4"
Bays 3 (26' 8" spacing)
$49,541
Estimated total (building + doors + trim)
$12.39
Per square foot
6,480 lb
Main frame steel weight

Prices as of September 2026.

Where the money goes

Each category includes 8.25% sales tax and a 15% markup, matching the app's defaults. Both are adjustable to your own numbers.

CategoryWhat's in itCost
Steel, sheet & trimI-beams, purlins, girts, eave struts, end wall columns, roof & wall sheets, one walk door, and all trim$42,370
Doors & WindowsTwo 12'×12' roll-up doors$7,170
Grand total$49,541

Main frame members

Columns and rafters are cut as separate pieces and nested onto stock lengths with the least waste; each row is the stock to buy and how it's cut. Weight is quantity × stock length × pounds per foot (the second number in the size: W12x19 is 19 lb/ft), which adds up to the 6,480 lb above.

Stock & cutsQtySizeLengthWeight
2 cut 1 × 26' 4 1/4" rafter, 2 × 14' 0" column · 5' 7 1/2" drop; 1 cut 2 × 26' 4 1/4" rafter · 7' 3 3/8" drop3W16x2660'4,680 lb
2 cut 1 × 26' 4 1/4" rafter, 2 × 14' 0" column · 5' 7 1/2" drop; 1 cut 2 × 26' 4 1/4" rafter · 7' 3 3/8" drop3W8x1060'1,800 lb
Total frame steel6,480 lb

Span charts behind these sizes

The highlighted rows set this building's sizes: a 50' clear span calls for W16x26 frames, and 26' 8" bays call for 10" roof purlins. These are the app's default charts.

Main frame · gable

Clear span up toBeam
30'W12x14
40'W12x19
50'W16x26
60'W18x35

Purlins & wall girts

Bay span up toC-section
20'6"
25'8"
30'10" (roof only)

Adjust them for your climate. Snow and wind loads vary by region, so every row is editable on the app's Settings tab. Change a size or a span break to match what your engineer or local code requires, and every new estimate uses your charts. More about span charts

Full material list

Wall, roof, and trim color: Charcoal Gray.

ItemQtySizeLengthNotes
1. I-Beams
I-beam stock3W16x2660'2 cut 1 × 26' 4 1/4" rafter, 2 × 14' 0" column · 5' 7 1/2" drop; 1 cut 2 × 26' 4 1/4" rafter · 7' 3 3/8" drop
I-beam stock3W8x1060'2 cut 1 × 26' 4 1/4" rafter, 2 × 14' 0" column · 5' 7 1/2" drop; 1 cut 2 × 26' 4 1/4" rafter · 7' 3 3/8" drop
Tube stock2TS4x4x.18824'cut each 1 × 22' 4" center column · 1' 8" drop
Weld plates26" × 6"—one per column · 2 end wall center columns (TS4x4x.188)
Weld plates46" × 12"—one per column · 4 end wall frame columns (W8x10)
Weld plates48" × 20"—one per column · 4 interior frame columns (W16x26)
2. Purlins, Girts & Eave Struts
Roof purlins4210"30'
Eave struts610"30'4:12 pitch
Sidewall girts188"30'
Gable end girts128"25'
Above-eave girt (+7')28"20'
Jamb purlins28"20'nested — 4 jambs cut from these
Jamb purlins28"25'nested — 4 jambs cut from these
Header purlins18"25'nested — 2 headers cut from these
3. Roof & Wall Sheets
Roof panels54—26' 5"
Sidewall panels54—14' 0"
Gable end panels36—14' 4" – 22' 4"4 @ 22' 4", 4 @ 21' 4", 4 @ 20' 4", 4 @ 19' 4", 4 @ 18' 4", 4 @ 17' 4", 4 @ 16' 4", 4 @ 15' 4", 4 @ 14' 4" (12" wide) · 36" wide
4. Trim
Ridge cap8—12'12" overlap · 4:12 pitch
Rake trim8—mixed4 @ 22' 0" full-length, 4 @ 6' 4" seam piece · roof length + 1', seamed w/ 12" overlap
Eave trim16—12'12" overlap · 4:12 pitch
Outside corners4—15' 0"sidewall height + 1', seamed w/ 12" overlap
Base angle11—25'full slab perimeter, 12" overlap
Rake angle8—25'end wall beams, full roof length, 12" overlap
Head trim (walk doors)1—3' 6"top
Head trim (roll-up doors)2—13' 0"top
Jamb trim (walk doors)2—7' 6"both sides
Jamb trim (roll-up doors)4—13' 0"both sides
Jamb wrap (roll-up doors)2—13' 0"top
Jamb wrap (roll-up doors)4—13' 0"both sides
5. Accessories
Peak boxes2——one per gable end
Rake end caps4—pairleft/right pair per rake run
Purlin clips172——2 per piece · 86 pieces to clip
Walk doors1—3' 0" × 7' 0"Right sidewall · bay 1 · centered · White
6. Doors & Windows
Roll-up door2—12' 0" × 12' 0"Front gable end · bays 1–2 · centered · Polar White
Steel, sheet & trim$42,370
Doors & Windows$7,170
Grand total$49,541

Rough budgeting estimate, not a mill quote. Doesn't include permits, engineering, delivery, concrete, labor, or insulation (the Pro plans price those on top of the same takeoff). Prices use the app's default rates; your supplier pricing will differ.

What a 50x80 shop changes

At 50' of clear span the main frame steps up to W16x26, and the 14' eave sets the column length; columns and rafters are cut from beam stock nested for the least waste. The 80' depth splits into 3 bays of 26' 8", which calls for 10" roof purlins in 30' sticks. The two 12'×12' doors are why the eave is 14': a 12' door needs headroom above it for the header and the door's roll.

Common questions

How much does a 50x80 metal shop cost?
At the app's default prices (September 2026), a 50x80 weld-up shop with a 14' eave, 4:12 pitch, one walk door and two 12'×12' roll-up doors comes to $49,541, or $12.39 per square foot. That's the building package: steel, sheets, trim, doors and windows, with sales tax and a 15% markup.
What does a 50x80 cost erected on a slab?
About $135,561, or $33.89 per square foot: $49,541 for the building package, $32,200 for erection labor and $53,820 for the slab. Insulation, site work and permits are on top.
How much steel is in a 50x80?
The main frames are 6,480 lb of W16x26 beam. Purlins, girts and eave struts are light-gauge C-sections on top of that, listed in the full material list below.

See it before you order it

This same 50x80 draws itself in the app. Pick your wall, roof, trim, door, and wainscot colors and the building repaints in 3D; switch to the wireframe to check where the purlins, girts, eave struts, and jamb purlins land. Eight views — four isometric corners and four straight-on elevations — so you can look at a door from outside or the framing from the corner you'll erect from.

Change any dimension and get your own real takeoff.